The project is comprised of one field sized for multi-use sports with a very high-grade carpet and the second field is a soccer field made with a lower grade carpet. The fields are on terraces formed on a hillside, complicated by pockets of poor soil and bedrock outcrops. Stormwater Detention Pond placed at the toe of slope projects downstream water courses from flooding. The fields have stood up very well to high use even in a major rain event. Our firm provided full-service support from concept and facilitation through to fulltime site inspection. Enhancements to the clubhouse, parking lot, driveway, landscaping and signage were further implemented by Glenn Group in 2013.
The Town engaged Glenn Group in the Fall (2018) to prepare a technical specification and an RFP for the replacement of the soccer field turf in 2019.